ISAB S.R.L Priolo Gargallo
Adaptation of three methanol tanks inside the ISAB Nord plants refinery, refurbishment of the sewage system and waterproofing of the basins
The works carried out concern the adaptation of three methanol tanks inside the ISAB Impianti Nord refinery with respect to the new environmental regulations, the reconstruction of the related sewage system and the waterproofing of the geo-membrane laying basins and concrete casting. The works also involved demolitions, metal carpentry works, special flooring and restoration of damaged parts.
Some details about the works:
CLIENT: ISAB S.r.l.
PLACE: Raffineria ISAB – Priolo Gargallo (SR)
START OF THE WORK: 06/2016
END OF THE WORK: 01/2017
WORK AMOUNT: € 1.017.028
MAN HOURS: 20.000