ENEL S.P.A. Augusta Power Plant (SR)

Works for the execution of seismic reinforcements in the Machine Room and ancillary civil works for the construction of a biomass plant at the "Orso Maria Corbino" power plant in Augusta (SR).

https://www.solesi.it/wp-content/uploads/2020/12/1-copertina-1.jpg
https://www.solesi.it/wp-content/uploads/2020/12/2-8.jpg
https://www.solesi.it/wp-content/uploads/2020/12/3-7.jpg
https://www.solesi.it/wp-content/uploads/2020/12/4-7.jpg

Project: ENEL S.P.A. Augusta Power Plant (SR)

Title:

Description:

ENEL S.P.A. Augusta Power Plant (SR)

Works for the execution of seismic reinforcements in the Machine Room and ancillary civil works for the construction of a biomass plant at the "Orso Maria Corbino" power plant in Augusta (SR).

https://www.solesi.it/wp-content/uploads/2020/12/1-copertina-1-540x540.jpg
https://www.solesi.it/wp-content/uploads/2020/12/2-8-540x540.jpg
https://www.solesi.it/wp-content/uploads/2020/12/3-7-540x540.jpg
https://www.solesi.it/wp-content/uploads/2020/12/4-7-540x540.jpg

Job description

As part of the “Futur-E” project, aimed at the redevelopment of production sites no longer in use, ENEL S.p.A. has started the construction of a new biomass plant.

For the construction of the new plant, Solesi S.p.A. oversaw the execution of the seismic reinforcements of the previous Machine Room of the Enel “Orso Mario Corbino” plant, the construction of civil works relating to the adaptation of the engine room and the execution of the systems for connecting to the MV network and for safeguarding existing users , as well as the execution of the renovation of the roof of the Machine Room building.

Below is the list of the main activities carried out by the company as part of the project:

1. excavation, demolition and filling;
2. execution of foundations with micropiles;
3. castings of reinforced concrete curbs for connecting metal structures and for stiffening by means of steel plates and tie rods;
4. reinforcement of beams in elevation;
5. realization of various finishing works;
6. execution of concrete works.
7. assembly of metal structures.

CLIENT: ENEL S.P.A.
PLACE: Enel plant “Orso Mario Corbino” in Augusta (SR)
START OF THE WORK: 05/2018
END OF THE WORK: 10/12/2020
AMOUNT OF THE WORK: 1.820.000
ORE UOMO: 25.000


Sede legale

Via Stentinello, 9 int. 13
96100 Siracusa
Tel.: 0931/751411
Fax: 0931/756944
Email: solesi@solesi.it

Sede commerciale

Via Carlo De Angeli, 3
20141 Milano Tel.: 02/6694125
Fax: 02/6694145
Email: solesi.milano@solesi.it

Branch estere

Belgium Branch - Brussels
Denmark Branch - Roskilde
France Branch - Lyon
Poland Branch - Poznan
Slovakia Branch - Bratislava

Gruppo irem

Via Stentinello, 9
96100 Siracusa
Tel.: 0931/787011
Fax: 0931/756875
Email: irem@iremspa.it