FLUXYS GAS COMPRESSION STATION
Execution of civil works for the realization of a new gas compression unit within the Berneau station.
The structures for the expansion of the gas compression station involved the construction of the following works:
Five new buildings in the RTR area:
Three new buildings in the SEGEO area:
Excavations, embankments and earth movements, demolitions, reinforced concrete foundations for buildings, c.a.p. buildings, foundations for pipe-racks and metal structures, foundations for systems, various foundations and for tanks, grouting, underground networks, road works, earth networks, metal carpentry.
CLIENT: Renco Belgium Branch
PLACE: Berneau – Belgium
START OF THE WORK: 07/2010
END OF THE WORK: 07/2012
WORK AMOUNT: € 6.800.000
MAN HOURS: 136.000